Legislature(2015 - 2016)BARNES 124

01/25/2016 01:00 PM House RESOURCES

Note: the audio and video recordings are distinct records and are obtained from different sources. As such there may be key differences between the two. The audio recordings are captured by our records offices as the official record of the meeting and will have more accurate timestamps. Use the icons to switch between them.

Download Mp3. <- Right click and save file as

Audio Topic
01:06:50 PM Start
01:08:24 PM Presentation(s): Alaska Liquefied Natural Gas Project by Steve Butt, Senior Project Manager
02:38:14 PM Adjourn
* first hearing in first committee of referral
+ teleconferenced
= bill was previously heard/scheduled
+ Update: TELECONFERENCED
AKLNG Project by Manager Steve Butt
-- Testimony <Invitation Only> --
                    ALASKA STATE LEGISLATURE                                                                                  
               HOUSE RESOURCES STANDING COMMITTEE                                                                             
                        January 25, 2016                                                                                        
                           1:06 p.m.                                                                                            
                                                                                                                                
MEMBERS PRESENT                                                                                                               
                                                                                                                                
Representative Benjamin Nageak, Co-Chair                                                                                        
Representative David Talerico, Co-Chair                                                                                         
Representative Bob Herron                                                                                                       
Representative Craig Johnson                                                                                                    
Representative Kurt Olson                                                                                                       
Representative Paul Seaton                                                                                                      
Representative Andy Josephson                                                                                                   
Representative Geran Tarr                                                                                                       
                                                                                                                                
MEMBERS ABSENT                                                                                                                
                                                                                                                                
Representative Mike Hawker, Vice Chair                                                                                          
                                                                                                                                
COMMITTEE CALENDAR                                                                                                            
                                                                                                                                
PRESENTATION(S):  ALASKA LIQUEFIED NATURAL GAS (AK LNG) PROJECT                                                                 
BY STEVE BUTT, SENIOR PROJECT MANAGER                                                                                           
                                                                                                                                
     - HEARD                                                                                                                    
                                                                                                                                
PREVIOUS COMMITTEE ACTION                                                                                                     
                                                                                                                                
No previous action to record                                                                                                    
                                                                                                                                
WITNESS REGISTER                                                                                                              
                                                                                                                                
STEVE BUTT, Senior Project Manager                                                                                              
Alaska LNG Project                                                                                                              
ExxonMobil Development Company                                                                                                  
Houston, Texas                                                                                                                  
POSITION STATEMENT:  Provided a PowerPoint update on the Alaska                                                               
Liquefied Natural Gas (AK LNG) Project.                                                                                         
                                                                                                                                
                                                                                                                                
ACTION NARRATIVE                                                                                                              
                                                                                                                                
1:06:50 PM                                                                                                                    
                                                                                                                                
CO-CHAIR BENJAMIN NAGEAK called the House Resources Standing                                                                  
Committee meeting to order at 1:06 p.m.  Representatives Seaton,                                                                
Tarr, Olson, Josephson. Talerico, and  Nageak were present at the                                                               
call to  order.   Representatives Johnson  and Herron  arrived as                                                               
the  meeting  was in  progress.  Representative  Colver was  also                                                               
present.                                                                                                                        
                                                                                                                                
CO-CHAIR  NAGEAK  thanked  the Department  of  Natural  Resources                                                               
(DNR) for assisting  in getting the new  up-to-date resource maps                                                               
displayed on the committee room walls.                                                                                          
                                                                                                                                
^PRESENTATION(S):  Alaska Liquefied Natural  Gas Project by Steve                                                               
Butt, Senior Project Manager                                                                                                    
PRESENTATION(S):  Alaska Liquefied Natural Gas (AK LNG) Project                                                             
             by Steve Butt, Senior Project Manager                                                                          
                                                                                                                              
1:08:24 PM                                                                                                                    
                                                                                                                                
CO-CHAIR NAGEAK announced  that the only order of  business is an                                                               
update on  the Alaska Liquefied  Natural Gas (AK LNG)  Project by                                                               
Steve Butt, Senior Project Manager.                                                                                             
                                                                                                                                
1:08:33 PM                                                                                                                    
                                                                                                                                
STEVE  BUTT,   Senior  Project   Manager,  Alaska   LNG  Project,                                                               
ExxonMobil  Development Company,  noted  that today's  PowerPoint                                                               
update on  the Alaska Liquefied  Natural Gas (AK LNG)  Project is                                                               
the first of three updates in  2016 as required under Senate Bill                                                               
138  [passed  and signed  into  law  in 2014].    He  said he  is                                                               
representing the work  of the [four] members of  the project team                                                               
[State  of   Alaska  through   the  Alaska   Gasline  Development                                                               
Corporation  (AGDC), BP,  ConocoPhillips, and  ExxonMobil].   The                                                               
project team  views itself as  a project  organization evaluating                                                               
the technical and  economic viability of the  Alaska LNG Project.                                                               
When providing  these updates the  team views legislators  as the                                                               
board  of directors  for  the shareholders,  the  public who,  as                                                               
owners, help make the decisions  around funding and directing the                                                               
project.   He said he  will be  speaking about what  has happened                                                               
since the last update that was given in September [2015].                                                                       
                                                                                                                                
1:10:45 PM                                                                                                                    
                                                                                                                                
MR.  BUTT turned  to slide  2, "Alaska  LNG -  Project Overview,"                                                               
explaining that  the objective  of the Alaska  LNG Project  is to                                                               
treat, transport,  and liquefy the  gas on  the North Slope  in a                                                               
manner that  can be  commercially attractive.   This means  a way                                                               
must be  found to  clean up  the gas, move  it across  the state,                                                               
make it  cold, and ship  it to consumers  in markets that  are in                                                               
need of  energy.   As the  owner, Alaska is  the seller  and must                                                               
think in the  construct of what makes sense for  the seller.  The                                                               
seller must think about how to  deliver gas/energy at a cost that                                                               
is competitive  with, or less  than, all the other  projects that                                                               
are trying to capture the same market.                                                                                          
                                                                                                                                
1:12:14 PM                                                                                                                    
                                                                                                                                
MR. BUTT said  the Alaska LNG Project is anchored  by the Prudhoe                                                               
Bay and Point  Thomson fields where it is thought  that there are                                                               
32-35 trillion cubic feet (TCF) of  gas.  The project would build                                                               
a transmission  line between Point  Thomson and Prudhoe  Bay that                                                               
the  Point Thomson  owners would  carry.   A gas  treatment plant                                                               
(GTP)  would be  built  [on  the North  Slope]  to remove  carbon                                                               
dioxide (CO)  and other  impurities.  He explained  that CO  is a                                                               
           22                                                                                                                   
by-product  of reservoirs,  with most  reservoirs having  about 4                                                               
percent CO  but Prudhoe Bay having  12 percent CO.   No other LNG                                                               
          22                                                                                                                    
projects in  the world  today are  treating reservoirs  with that                                                               
much CO.   A huge element of the Alaska  LNG Project is to find a                                                               
       2                                                                                                                        
way to  efficiently treat the  gas and put those  impurities back                                                               
in the  ground.   After treatment  the gas  would be  moved south                                                               
through an  804-mile-long pipeline from  Prudhoe Bay to  the lead                                                               
project  site located  outside of  Nikiski.   The pipeline  would                                                               
handle about 3.3-3.5 billion cubic  feet of gas [per day] (BCFD).                                                               
Mr.  Butt explained  that these  numbers move  with fuel  and in-                                                               
state demand because  more gas is used for heating  in the winter                                                               
than  in  the   summer.    The  gas  would  be   brought  to  the                                                               
liquefaction  facility to  be cooled  to -260  degrees Fahrenheit                                                               
(F).   At -260  degrees F,  methane gas turns  into a  liquid and                                                               
shrinks by  a factor  of 600.   The cooling is  done in  order to                                                               
deliver a  certain volume  of gas  to foreign  markets and  it is                                                               
much easier  to deliver one cargo  of liquid gas than  600 cargos                                                               
of gas  in a  vapor phase.   In summary,  the Alaska  LNG Project                                                               
would  treat the  gas to  remove impurities,  transport the  gas,                                                               
provide gas to Alaskans, and cool the gas so it can be exported.                                                                
                                                                                                                                
1:14:50 PM                                                                                                                    
                                                                                                                                
MR.  BUTT  stated  that  the   Alaska  LNG  Project  has  several                                                               
advantages.  The is being located  in Alaska where the weather is                                                               
cooler  and drier  relative to  other places  where LNG  is made,                                                               
which  allows the  gas  to be  liquefied  much more  efficiently.                                                               
Compared to the Middle East, an  LNG plant can be built in Alaska                                                               
with the  same horsepower  and same  equipment and  produce 10-15                                                               
percent more  LNG.   Another advantage is  being in  the Northern                                                               
Hemisphere.  When it is cold in  Alaska it is also cold where the                                                               
buyers  are.   Because  compression equipment  is more  efficient                                                               
when it is  cold it makes more  LNG when it is  cold.  Therefore,                                                               
the  project is  making more  LNG  in January  and February  when                                                               
everyone wants to buy it.   Many of the project's competitors are                                                               
in the Southern Hemisphere, so those  places have to add a lot of                                                               
compression and  make their  plants bigger because  it is  hot in                                                               
January in  the Southern  Hemisphere.   To handle  the difference                                                               
between the  southern and northern hemispheres  those competitors                                                               
must spend  more money  than does  the Alaska  LNG Project.   The                                                               
third  and most  important  advantage is  being  anchored by  the                                                               
known resources  of Prudhoe Bay  and Point Thomson.   The Prudhoe                                                               
Bay operator  has been maximizing  oil production  by reinjecting                                                               
the gas  back into the  ground.  There  is no resource  risk like                                                               
many other  projects because  Prudhoe Bay  has produced  7-9 BCFD                                                               
every day for the  last 30-plus years and has put  it all back in                                                               
the ground.  The project's  federal regulator, the Federal Energy                                                               
Regulatory  Commission  (FERC),  is  pleased  that  the  upstream                                                               
infrastructure  is  already developed  and  that  the project  is                                                               
taking advantage of a known resource.                                                                                           
                                                                                                                                
MR. BUTT  said these strong  advantages offset the  challenges of                                                               
the high CO  levels at Prudhoe Bay that require a lot of treating                                                               
           2                                                                                                                    
and having to move the gas 800  miles from [the North Slope] to a                                                               
port that can operate for 12 months  out of the year.  The Alaska                                                               
LNG  Project   must  pay  for   this  infrastructure,   which  is                                                               
infrastructure that most other projects  do not have.  While some                                                               
LNG  projects operating  in the  world  have about  400 miles  of                                                               
pipeline, no project has 800 miles.                                                                                             
                                                                                                                                
1:17:10 PM                                                                                                                    
                                                                                                                                
MR.  BUTT addressed  slide 3,  "Alaska LNG  - Status,"  reporting                                                               
that the  team completed all work  in 2015, about a  half million                                                               
hours  in the  field and  in the  office, without  any incidents.                                                               
One incident occurred in 2014 and  none occurred in 2013 or 2012.                                                               
The project continues  to build a culture of  caring where people                                                               
are aware of their actions and are making safe choices.                                                                         
                                                                                                                                
MR.  BUTT advised  that the  project spent  about $83  million in                                                               
2014 and  about $293  million in  2015, for  a total  spending of                                                               
about $376 million on Pre-Front-End Engineering and Design (Pre-                                                              
FEED) as of closing the books for  2015.  In addition to the Pre-                                                               
FEED expenditures about  $170 million was spent  on concept work,                                                               
for  a total  expenditure  so far  of about  $480  million.   The                                                               
Alaska Gasline  Development Corporation (AGDC)  recently provided                                                               
information in  the public domain  that the approved  2016 budget                                                               
is $230  million, although  efforts will  be made  to try  not to                                                               
spend that  much.  The  initial design  work that was  defined in                                                               
the June 2014  joint venture agreement (JVA) is  about 85 percent                                                               
complete.  However, that does not  include the work being done on                                                               
the 48-inch  pipeline; when  that is included  the work  is about                                                               
70-75 percent complete.   The JVA goes out to  the middle of 2017                                                               
and when looking at what needs to  be done in 2016 the project is                                                               
on track.                                                                                                                       
                                                                                                                                
1:20:24 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE  OLSON asked  what  the cost  is  for the  48-inch                                                               
pipeline study.                                                                                                                 
                                                                                                                                
MR. BUTT replied that it was  scoped at about $30 million but may                                                               
get done for $26 or $27 million.                                                                                                
                                                                                                                                
1:20:51 PM                                                                                                                    
                                                                                                                                
MR. BUTT returned to slide  3, explaining that the aforementioned                                                               
all goes into the execution basis  for cost and schedule.  One of                                                               
the  most  important deliverables  in  the  Pre-FEED phase  is  a                                                               
really good  estimate of what the  project will cost.   The range                                                               
of between $45  and $65 billion has always been  used.  While the                                                               
estimate will  remain within  that range, he  said he  would like                                                               
the cost to be at $45  billion, not $65 billion.  Progressing the                                                               
regulatory work done  in 2015 will continue in 2016,  and this is                                                               
viewed as critical path because  if this slides everything slides                                                               
with  it.   The FERC  work is  viewed as  critical path  because,                                                               
until more  certainty is  had on  the regulatory  environment and                                                               
the  permit, it  is  hard for  the team  to  make decisions;  for                                                               
example,  labor  and  logistics  hinge  on  when  the  permit  is                                                               
received  to construct.    While the  project  continues to  have                                                               
great support from FERC, it does  not have certainty on when [the                                                               
permit]  will be  done.    The Alaska  LNG  Project has  received                                                               
export  authorizations  for  both free-trade  and  non-free-trade                                                               
countries, making the  project one of just a handful  in the U.S.                                                               
that have the  right to export gas.  Outside  the project domain,                                                               
the  Prudhoe Bay  and  Point Thomson  operators  worked with  the                                                               
Alaska Oil  and Gas  Conservation Commission  (AOGCC) to  get the                                                               
right to offtake  gas.  Prior to that work  neither Point Thomson                                                               
nor Prudhoe Bay had the right  to deliver gas to the project; so,                                                               
from a  project perspective this  was a  big risk given  that the                                                               
project is talking  about building a $45-$65  billion project and                                                               
nobody had  right to give the  project gas.  A  step forward like                                                               
this is called de-risking.                                                                                                      
                                                                                                                                
1:23:29 PM                                                                                                                    
                                                                                                                                
MR.  BUTT reported  that  in  2016 the  Alaska  LNG Project  will                                                               
continue  its   Pre-FEED  work   and  its   environmental  impact                                                               
statement  (EIS),  which is  the  product  of the  FERC  resource                                                               
reports.    The   resource  reports  inform  the   EIS,  and  the                                                               
completion  of   the  EIS  allows   the  project  to   secure  an                                                               
authorization to  construct.  Work  on the 48-inch  pipeline will                                                               
be finished in  the second quarter and the team  will try to make                                                               
its  decision in  April  2016  on which  size  makes more  sense.                                                               
Geotechnical  and  geophysical  work  (G&G)  will  be  continued.                                                               
Field work will continue to  finish the resource reports to FERC;                                                               
FERC wants  one set  of drafts  written in  pencil, a  second set                                                               
written in pen,  and then a final application.   The pencil draft                                                               
was  provided to  FERC  in first  quarter 2014  and  many of  the                                                               
components of the pen draft are  finished.  In 2016 the team will                                                               
also do  a lot with contracting  strategy - how to  make sure the                                                               
project  will  be  globally competitive  and  engage  global  LNG                                                               
companies  with local  Alaskan  companies.   The  team will  keep                                                               
trying  to  provide owners  with  information  for the  Front-End                                                               
Engineering and Design (FEED) decision.                                                                                         
                                                                                                                                
MR. BUTT pointed out that a  strength of this project is that for                                                               
the first time ever  all four parties with a claim  to the gas on                                                               
the  North  Slope are  working  together.   The  three  producers                                                               
bought  the right  to produce  the hydrocarbons  from the  State.                                                               
The State  receives its share  of revenue as a  derivative right.                                                               
All  four of  those  parties have  a claim  to  that resource  in                                                               
different ways, but this is the  first time all four parties have                                                               
tried  to  come together  and  work  out  all the  myriad  issues                                                               
associated  with making  that happen.   As  a board  of directors                                                               
group for the  owners, legislators need information  to make this                                                               
decision that  will be  coming up  later this  year or  middle of                                                               
next  year,  and  the  legislative   updates  will  provide  this                                                               
information.                                                                                                                    
                                                                                                                                
1:25:42 PM                                                                                                                    
                                                                                                                                
MR. BUTT reviewed  several key messages.  The first,  he said, is                                                               
that the  Alaska LNG Project is  an integrated LNG project.   The                                                               
plants are really  important and are three-quarters  of the cost.                                                               
Without the  LNG plant there is  not the ability to  underpin the                                                               
economy  of  scale  necessary  to make  the  whole  project  work                                                               
because  the amount  of gas  Alaskans use  is a  fraction of  the                                                               
amount of gas  the project will be handling.   Alaskans use about                                                               
250 million  cubic feet of  gas a  day on average;  AGDC's recent                                                               
study  was about  220  million.   However,  the  project will  be                                                               
sending 10  times that amount  - about  2.4 billion cubic  feet a                                                               
day to export markets, enough gas  to fuel an economy the size of                                                               
Germany -  and the State has  enough gas to do  that for decades.                                                               
Having the ability  to liquefy that gas and get  an export market                                                               
to  underpin the  project will  attract interest  from investors,                                                               
lenders,  and buyers  to make  a project  like this  work.   This                                                               
project  cannot be  done if  it isn't  integrated and  that comes                                                               
back to  the gas treatment plant.   The CO  must be  taken out of                                                               
                                          2                                                                                     
the gas and put back  in the ground because CO  has no beneficial                                                               
                                              2                                                                                 
use and  it freezes at  [-50] degrees F.   In trying to  make gas                                                               
really  cold at  -260 degrees  F and  with  CO  freezing at  -50,                                                               
                                              2                                                                                 
everything that  the CO  touches  freezes.   So, the CO   must be                                                               
                       22                                                                                                       
removed to  prevent damage  to the plant  and stopping  the plant                                                               
from running.   The  CO  cannot  be vented  as an  alternative to                                                               
                       2                                                                                                        
being put  back in the ground  because it has adverse  impacts on                                                               
the environment, so  the project must meet this head  on and make                                                               
sure there is the ability to reinject the gas at Prudhoe Bay.                                                                   
                                                                                                                                
1:27:23 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE  OLSON inquired  about  the CO   content at  Point                                                               
                                             2                                                                                  
Thomson.                                                                                                                        
                                                                                                                                
MR. BUTT responded that the  Point Thomson CO  content is about 4                                                               
                                             2                                                                                  
percent, much  less than [the 12  percent at] Prudhoe Bay.   Most                                                               
reservoirs are about  4 percent and most LNG projects  are in the                                                               
2-4 percent range.  It is  uncommon to liquefy gas with more than                                                               
4 percent CO  - there  is only one, in Western  Australia, and it                                                               
            2                                                                                                                   
will  be  coming  online  sometime   in  the  next  9-12  months.                                                               
Combining Point  Thomson and  Prudhoe Bay  gas will  help because                                                               
the blended stream has less  CO than Prudhoe  Bay alone.  The gas                                                               
                               2                                                                                                
treatment plant must  be built to handle the gas  at Prudhoe Bay.                                                               
Whether for the 10.5 percent  blended value of Point Thomson plus                                                               
Prudhoe Bay or just for Prudhoe  Bay, the size of the facility is                                                               
about the same.                                                                                                                 
                                                                                                                                
1:28:32 PM                                                                                                                    
                                                                                                                                
MR. BUTT resumed his discussion  of slide 3, stating that another                                                               
key message is  that low cost of supply wins.   Everything in the                                                               
LNG market is  about cost.  People want the  utility value of the                                                               
gas; it  is not Copper  River salmon,  nobody will pay  extra for                                                               
it.   It is very  competitive and people  will pay just  a little                                                               
bit  less than  they can  get  it for  from somebody  else.   The                                                               
Alaska LNG Project  has to be that reliable supplier  that can be                                                               
cost  competitive.   Today's low  oil prices  show how  important                                                               
cost is and also  show that prices go up and  down.  What matters                                                               
in a  project world is  whether the participants can  find enough                                                               
alignment to  work together, that  they trust each other  so that                                                               
when  markets  come up  and  down  they  can work  through  those                                                               
problems   because  there   are   always  problems.     Can   the                                                               
participants build  a system that  is resilient enough  that when                                                               
prices go  up and down  they can survive the  downs?  Is  there a                                                               
little bit  left over when  the market is  down so that  when the                                                               
market is  up there is  the ability to  pay everything back?   He                                                               
urged that  legislators, as representatives of  the owners, think                                                               
about this as he shares information in this regard.                                                                             
                                                                                                                                
MR. BUTT advised  that low oil price isn't so  much about whether                                                               
the project  makes sense at $30  given that the project  will not                                                               
pencil to  come online  until 2025  or so.   Rather, it  is about                                                               
what the  price might be in  2025 or, more importantly,  what the                                                               
price might be  in 2040 since the Alaska LNG  Project has a 25-40                                                               
year life.   What will  make the project  work is the  ability to                                                               
resolve  the  issues  so  that  all parties  see  a  benefit  for                                                               
themselves and  can move  forward.  Low  prices just  sharpen the                                                               
participants'  focus.    He  related  that  one  of  the  biggest                                                               
projects he was  involved in during his 30-plus  years of project                                                               
work was done at  an oil price of $9 because  the project had the                                                               
ability to look far ahead.                                                                                                      
                                                                                                                                
MR.  BUTT stressed  it  is  critical for  owners  to think  about                                                               
whether the project  would be losing money on a  unit cost basis.                                                               
If the  project cannot deliver gas  cheap enough that there  is a                                                               
margin when the  prices are down, the project cannot  make up for                                                               
it  on volume.   It  cannot be  offset because  it takes  so much                                                               
money up front:   $45-$65 billion must be spent  to ship the very                                                               
first molecule  of gas  and then every  molecule after  that gets                                                               
cheaper.  This is why the whole  life of the project, the cost of                                                               
supply, must be  looked at.  The cost of  supply is calculated by                                                               
adding  together  all   the  costs  to  build   and  operate  the                                                               
facilities and ship the gas and  then dividing that by the amount                                                               
of  gas that  will be  shipped.   The critical  question for  the                                                               
project's owners  is whether the  project can supply  markets for                                                               
less  than another  supplier.   Mr.  Butt explained  that in  his                                                               
project leadership  role he must test  how to drive down  cost of                                                               
supply:   testing how to get  more LNG for less  cost by changing                                                               
machinery  configurations,  design configurations,  and  material                                                               
sources.   That is what  boards of directors  - owners -  need to                                                               
hear and  that is the  message he  is bringing to  the committee.                                                               
Mr. Butt further  pointed out that risk is the  other side of the                                                               
coin.  One  risk is the price  going down.  Another  risk was not                                                               
having  gas  offtake,  but  now  there is  gas  offtake  so  that                                                               
particular risk is gone.                                                                                                        
                                                                                                                                
1:32:36 PM                                                                                                                    
                                                                                                                                
MR.  BUTT moved  to slide  4,  "Project Design  Basis -  Update,"                                                               
informing committee  members that the integrated  design basis is                                                               
pretty much  finished.  He explained  that detailed compositional                                                               
and hydraulic  analyses have  been done on  the gas  from Prudhoe                                                               
Bay and Point  Thomson, meaning a look was taken  at every single                                                               
molecule of every single  hydrocarbon and non-hydrocarbon element                                                               
in the gas to see how  much is methane, ethane, liquids, propane,                                                               
and so on,  all of which can  be used.  An  integrated system has                                                               
now  been  built  from  these  analyses.    The  system  is  very                                                               
interdependent.   For example, changing the  delivery temperature                                                               
of  the  compression facilities  at  Point  Thomson by  about  10                                                               
degrees  results  in   moving  hundreds  of  barrels   a  day  of                                                               
condensate across the  whole system.  This is  because instead of                                                               
stripping it out at  the top it moves all the  way to the bottom.                                                               
So, decisions must be made about what  is the best way to put the                                                               
equipment,  what is  the  right temperature,  what  is the  right                                                               
pressure to drive down cost of supply.                                                                                          
                                                                                                                                
MR. BUTT explained that modeling  and analyses are done to ensure                                                               
the project  is fit-for-purpose.   Fit-for-purpose is the  way of                                                               
saying at  the lowest possible cost  without compromising safety,                                                               
ability to deliver, or reliability.   The next thing that is done                                                               
is  called reliability,  availability, and  maintainability (RAM)                                                               
modeling.   It  is detailed  modeling  over a  40-year period  of                                                               
every piece  of equipment to  ensure that the  maintenance cycles                                                               
are not conflicting - that when work  is needed on the GTP in the                                                               
north,  work can  also be  done on  the LNG  plant in  the south.                                                               
This  allows the  work to  be  matched up  because the  different                                                               
pieces of  equipment have different  life cycles.   All equipment                                                               
needs maintenance,  but some need  maintenance every  5,000 hours                                                               
and some every 10,000 hours.   So, machinery selection and design                                                               
work must  be done  to ensure  that it all  syncs up  and remains                                                               
balanced to help  drive down costs; for example,  there are three                                                               
gas treatment trains and three LNG trains.                                                                                      
                                                                                                                                
1:35:12 PM                                                                                                                    
                                                                                                                                
MR.  BUTT  discussed slide  5,  "LNG  Plant and  Marine  Terminal                                                               
Update,"  noting that  the top  right picture  shows how  a barge                                                               
(depicted  with  the  red  line) would  deliver  a  module  (tall                                                               
structure in  the center  of the  picture) to  a roll-on/roll-off                                                               
(RORO) facility.  There is  also a lift-on/lift-off (LOLO), which                                                               
is a  crane facility so barges  and materials can be  loaded from                                                               
the side.  This work is complete  and it is now known exactly how                                                               
to  move all  the  equipment that  will be  needed  to build  the                                                               
facility.   The marine design  is continuing  to be looked  at to                                                               
ensure that  costs of the trestle  and the size of  the footprint                                                               
are minimized.   The geotechnical program was  successful with 61                                                               
boreholes drilled onshore, 25 boreholes  drilled offshore, and 20                                                               
monitoring wells drilled to ensure  it was understood what was in                                                               
the soil.   It  was confirmed that  the lead  site's geotechnical                                                               
considerations were  as expected -  extra money does not  need to                                                               
be put  into foundations.   The  site does  not have  folding and                                                               
faulting  that would  require  design  for handling  earthquakes.                                                               
There are a lot of  significant geotechnical features to the west                                                               
and to the south of the inlet, as  well as down the center of the                                                               
inlet, so  a site was  looked for  that didn't have  those risks.                                                               
The  drillings  were to  confirm  that  the aforementioned  risks                                                               
don't   exist  at   the  lead   site  and   that  fit-for-purpose                                                               
foundations can be designed for  these facilities that can handle                                                               
any  sort of  geotechnical or  seismic event.   Mr.  Butt further                                                               
reported that the LNG facility  design layouts have been finished                                                               
and it  is known where  all the different  pieces will go.   This                                                               
information goes  into the resource  reports so that  the permits                                                               
can be  received to build it.   The project has  now shifted into                                                               
optimization where the focus is on cost reduction.                                                                              
                                                                                                                                
1:37:54 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE TARR  recounted the  [7.1 magnitude  earthquake on                                                               
1/24/16]  that [affected  the Kenai  Peninsula].   She  recounted                                                               
that  road damage  occurred  fairly near  the  terminal site  and                                                               
asked whether there was anything from this that was a surprise.                                                                 
                                                                                                                                
MR.  BUTT replied  there were  no  surprises, what  was seen  was                                                               
consistent  with what  was thought.   He  agreed it  was a  major                                                               
seismic event but advised that the  design is to seismic load 9.0                                                               
and the  foundations and  so forth  are in the  right place.   He                                                               
explained that  one reason  for selecting  this site  was because                                                               
the  sediments there  are  relatively soft  and  do not  strongly                                                               
transfer the energy of a seismic event.                                                                                         
                                                                                                                                
1:38:55 PM                                                                                                                    
                                                                                                                                
MR. BUTT returned to slide  5 to discuss the optimization studies                                                               
being done.  He reported that  how to source the gas turbines and                                                               
how to make them smaller is  being looked at because gas turbines                                                               
are  one of  the most  expensive things  that must  be purchased.                                                               
Given  there  are several  sources  of  these gas  turbines,  the                                                               
project team  wants to create  a competitive environment  for the                                                               
most efficient turbine possible.   Because Alaska is cold and dry                                                               
and the gas  starts out cold a bigger turbine  may not be needed.                                                               
Also being  looked at  are current limiters,  he continued.   The                                                               
project  design  separates a  lot  of  the big  horsepower  users                                                               
between  the gas  treatment facility  in  the north  and the  LNG                                                               
plant in  the south,  thereby allowing  use of  different current                                                               
designs to manage  this.   A half billion  to one billion dollars                                                               
could possibly be  saved by redesigning the way  the power moves.                                                               
Modularization improvements are being looked  at as well - how to                                                               
get  all  the  pieces  of  equipment  to  come  together.    Tank                                                               
technology is being explored.   A conventional LNG tank is large,                                                               
covered with concrete,  very thick, and has lots of  foam to keep                                                               
the  gas at  -260 F.   Material  selection cannot  be compromised                                                               
because  it needs  to  be safe,  but the  project  team wants  to                                                               
optimize  the  insulating  characteristics  and  the  size  as  a                                                               
function of  the marine  design.  Another  potential is  less LNG                                                               
storage capacity  depending on how efficiently  the marine assets                                                               
can be  used.  Further,  the offloading facility is  being looked                                                               
at to  make sure it  is sized just right  for the modules  and it                                                               
must be able to handle any ice in the inlet.                                                                                    
                                                                                                                                
MR. BUTT  played a video of  the marine simulation work  that has                                                               
been done with the Alaska  Vocational Technical Center (AVTEC) in                                                               
Seward to  design the offloading  facility.  The  simulations are                                                               
done  with Alaskan  pilot unions  and are  like being  on a  real                                                               
ship.   He  explained that  modeling and  simulation are  done to                                                               
ensure  that the  materials and  different  vessels are  designed                                                               
properly for  being safely moved in  and out of the  dock and the                                                               
area.   This simulation is part  of the Pre-FEED design  phase to                                                               
make sure everything works and can be done right.                                                                               
                                                                                                                                
1:42:47 PM                                                                                                                    
                                                                                                                                
MR. BUTT  moved to  slide 7,  "Pipeline Update,"  announcing that                                                               
all of the 42-inch pipeline design  work has been completed.  All                                                               
the welding procedure  and coating procedure testing  is done, as                                                               
is the capability  characteristics of a 42-inch system.   He said                                                               
the 42-inch  pipe was sourced from  three mills, one in  the U.S.                                                               
and  two outside  the  U.S.   The  pipe was  put  into a  coating                                                               
simulator  because the  pipe  gets very  hot  when being  coated,                                                               
about   2,500   degrees   [F],  and   therefore   the   post-heat                                                               
characteristics  of the  pipe must  be tested.   Compression  and                                                               
tensile testing of  the pipe must also be done  with the Pipeline                                                               
Hazardous Materials  Safety Administration  (PHMSA).   The agency                                                               
defines  characteristics   of  each  test  to   ensure  that  the                                                               
materials selected  for the pipe  will be  safe under a  range of                                                               
conditions at factors far in  excess of anything that PHMSA could                                                               
envision.     Tests   include   stretching   and  bending   under                                                               
compression,   and   the   42-inch   pipe   demonstrated   proper                                                               
characteristics under a range of  characteristic far in excess of                                                               
anything that  would be  seen in  operating.   Mr. Butt  played a                                                               
video  demonstrating  the  42-inch   pipe  passing  a  full-scale                                                               
compressive pipe test.                                                                                                          
                                                                                                                                
MR. BUTT noted that hydraulic work has been initiated on the 48-                                                                
inch pipe, and execution planning is  also being done.  This pipe                                                               
will be  received in April and  similar tests will be  done on it                                                               
in second quarter 2016.  A  decision, hopefully in April, will be                                                               
made on the cost and  execution differentials between the 42- and                                                               
48-inch pipe sizes.   The other places where costs  are trying to                                                               
be  cut are  routing and  gravel use  in the  construction phase,                                                               
camps,  crack arrestor  and valve  positions, and  heater station                                                               
requirements.  Because heater stations  are very expensive a look                                                               
is being taken at whether one or two stations are needed.                                                                       
                                                                                                                                
1:47:10 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE  OLSON inquired  whether three  joints of  48-inch                                                               
pipe can be handled on a trailer.                                                                                               
                                                                                                                                
MR. BUTT replied no, a truckload  of 42-inch pipe is three joints                                                               
and a truckload  of 48-inch pipe is  two joints.  One  of the big                                                               
differences in execution  is that 30-50 percent  of capacity must                                                               
be added  for everything -  there would be  a lot more  trucks, a                                                               
bigger  hole must  be dug,  heavier  side booms  are needed,  and                                                               
bigger equipment  is needed to  hold the  heavier pipe.   The 42-                                                               
inch pipe is about 5,400 pounds  per joint, 48-inch pipe is about                                                               
7,500 pounds per joint.                                                                                                         
                                                                                                                                
1:47:58 PM                                                                                                                    
                                                                                                                                
CO-CHAIR  TALERICO  understood  there  is  a  difference  between                                                               
submerging 42-inch versus 48-inch pipe  across the bottom of Cook                                                               
Inlet.   He inquired whether  testing will be done  to [determine                                                               
whether there is the ability to submerge 48-inch pipe].                                                                         
                                                                                                                                
MR. BUTT  responded that putting 48-inch  pipe in the inlet  is a                                                               
little  tougher because  it  is  heavy.   When  placing pipe  the                                                               
pipe's desire  to follow  gravity and fall  must be  managed with                                                               
the ability to  move it laterally into  the inlet.  To  do that a                                                               
large barge  is established  with very  large anchor  patterns so                                                               
that the  barge is fixed.   Then the pipe  is moved from  a point                                                               
that is at or  under the shore.  How to enter  and exit the inlet                                                               
has yet to  be decided because that is difficult.   The pipe that                                                               
is being  pulled out is always  trying to fall and  the challenge                                                               
with the 48-inch  pipe is having the equipment that  can move the                                                               
pipe out far enough  and lay it.  The thinking is  that it can be                                                               
done with  either size of pipe  - the 42-inch pipe  will be hard,                                                               
the 48-inch  pipe will be harder.   The analysis to  evaluate the                                                               
two systems will  look at how much larger a  barge will be needed                                                               
and whether a bigger crane and heavier wench will be needed.                                                                    
                                                                                                                                
1:49:37 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE HERRON  asked what  the two most  critical factors                                                               
are in the decision besides the aforementioned.                                                                                 
                                                                                                                                
MR.  BUTT   replied  cost   and  risk   are  the   most  critical                                                               
characteristics.   Driving cost is  that the additional  pipe for                                                               
48-inches is  much heavier, so a  lot more steel must  be bought.                                                               
The flip  side, however,  is that less  compression is  needed so                                                               
fewer  compression stations  are required.   Right  now steel  is                                                               
getting cheaper faster  than is compression equipment,  so a hard                                                               
look is being taken at 48-inches  to try to understand out in the                                                               
future what that  relationship is going to look like.   A 42-inch                                                               
system  takes about  1.2  million  tons of  steel  and a  48-inch                                                               
system takes about  1.8-1.9 million tons.  More  steel would have                                                               
to  be bought,  but less  other stuff  would have  to be  bought.                                                               
Thus, for cost, what is really  being looked at is whether enough                                                               
of the other stuff can be cut  to offset the cost of extra steel.                                                               
For risk,  what must be  looked at is  whether there is  a bigger                                                               
environmental risk because  the footprint goes up  given that the                                                               
gravel  use goes  up, everything  gets  a little  bit bigger  and                                                               
heavier, and  the number of  trucks moving goes  up.  It  must be                                                               
determined whether all  of this can be done in  a manner that the                                                               
execution risks  can be managed.   So, for cost it  is a tradeoff                                                               
on  cost between  steel  and  equipment, and  for  risk  it is  a                                                               
tradeoff between bigger and smaller.                                                                                            
                                                                                                                                
1:51:25 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE JOHNSON inquired whether  there could be political                                                               
risk  since no  American  company manufactures  48-inch pipe  and                                                               
this could potentially cause some opposition in Washington, DC.                                                                 
                                                                                                                                
MR. BUTT confirmed  this is a risk  that is being looked  at.  He                                                               
said the  project team has conversed  with about 10 mills  in the                                                               
U.S. and  asked whether any  of them would  be willing to  make a                                                               
48-inch system.  The  mills are not as busy today  as they were a                                                               
year ago and  now there are more answers of  willingness to talk.                                                               
The large  amount of  pipe means  several years  of mill  run, he                                                               
explained.   The  team is  unsure about  sourcing it  all in  one                                                               
place  because it  is actually  five very  different sections  of                                                               
pipes.   The  section between  Point Thomson  and Prudhoe  Bay is                                                               
very different than  the section between Prudhoe Bay  and the top                                                               
of  Atigun Pass,  and that  section  is very  different than  the                                                               
section  between  Atigun  down  into  the  Susitna,  which  is  a                                                               
discontinuous permafrost area.   The section south  of Susitna is                                                               
a conventional  system and  the pipe in  the inlet  is different.                                                               
The only  thing in common  between these five  different sections                                                               
is that  their internal  diameter is  the same  so that  the pipe                                                               
system can be maintained.  Therefore  it is thought that the pipe                                                               
sections can  be sourced  differently and that  some of  the U.S.                                                               
mills  might be  able  make some  of  the conventional  sections,                                                               
whereas a wider net may need to  be cast for some of the heavier,                                                               
more  complex  sections.   Conversations  have  taken place  with                                                               
federal  regulators  on  how they  would  view  potential  import                                                               
duties should it  be chosen to import  any of this pipe.   In the                                                               
event that the pipe cannot be sourced  in the U.S., is it fair to                                                               
hit the  project with import  duties?  To  date there has  been a                                                               
willingness to have that conversation,  but like every risk it is                                                               
not  really done  until  it is  done.   He  added  that the  pipe                                                               
pictured on slide 7 is from a U.S. mill.                                                                                        
                                                                                                                                
1:53:52 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE TARR  surmised that a 48-inch  system would affect                                                               
the  supply of  pipe and  add time  to the  timeline.   She asked                                                               
whether this should be of concern.                                                                                              
                                                                                                                                
MR. BUTT  replied it is  not known  whether it really  would take                                                               
longer because it would depend on  who agreed to make it and what                                                               
else that mill  is making.  The  mills not being as  busy as they                                                               
were a year  ago is good [for the project]  and gives the project                                                               
some  flexibility.    However,  it  isn't  real  until  there  is                                                               
contract.  It can be said  with great certainty that 48-inch pipe                                                               
is harder  to make.   But, if enough  of the right  resources are                                                               
procured, the  right mill  is available, and  there is  the right                                                               
contracting structure that requires it  in the same timeframe, it                                                               
might be possible to do it  without losing time, which has always                                                               
been the  objective.   The project's  analysis of  comparing cost                                                               
and execution is  being done on the same timeframe  for both pipe                                                               
sizes - which is to say that cost moves, time doesn't.                                                                          
                                                                                                                                
1:55:22 PM                                                                                                                    
                                                                                                                                
MR. BUTT returned to his discussion  of slide 7, stating that the                                                               
Alaska LNG  Project continues to  have good cooperation  with the                                                               
folks  at the  Alaska Gasline  Development Corporation  (AGDC) on                                                               
routing and data sharing.                                                                                                       
                                                                                                                                
MR. BUTT  displayed slide  9, "Gas  Treatment Plant  Update," and                                                               
stressed  the  importance of  the  GTP  for  getting rid  of  450                                                               
million  cubic  feet of  CO  every  day,  which  is well  over  4                                                               
                           2                                                                                                    
trillion  cubic  feet  of  CO  over  the  life  of  the  project.                                                               
                             2                                                                                                  
Handling that staggering volume of CO  is what drives the size of                                                               
                                     2                                                                                          
the gas treatment plant.  The  design and layout has been figured                                                               
out.    Much  work  was  done with  Prudhoe  Bay  on  integration                                                               
opportunities and  making sure everything worked  from permitting                                                               
and  operating perspectives.   The  camp layout  was changed  and                                                               
refined to make it smaller and the  camp was moved off the pad so                                                               
less  gravel would  be  used.   Gravel is  one  of the  project's                                                               
biggest costs,  so the  gravel sourcing has  been tested  and the                                                               
ability to  get the pit-run gravel  that will be needed  has been                                                               
confirmed.  Between  6 and 10 million cubic yards  of gravel will                                                               
be  needed.   For comparison,  he  noted that  the [gravel]  mine                                                               
opened in  1974 for  all the facilities  has produced  18 million                                                               
cubic yards  of gravel.  Because  it does not have  enough gravel                                                               
for the Alaska LNG Project, a  new gravel source is needed.  Also                                                               
being looked at  for cost reduction are module  weight and layout                                                               
optimization for making  modules as small and  tight as possible,                                                               
electrical design  through different equipment  positioning, what                                                               
machinery will  be used  and the sources,  and utilities  such as                                                               
electricity.  Execution  is being looked at in  regard to whether                                                               
four sea  lifts are required.   There will  be well in  excess of                                                               
100  modules, each  weighing 6,000-9,000  tons,  and the  current                                                               
plans call for  getting them all up there over  four years, which                                                               
is four different  sea lift windows.  A hard  look is being taken                                                               
at whether the  first of three sea lifts could  bring up the camp                                                               
facility along  with modules,  rather than  bringing up  the camp                                                               
facility by itself.                                                                                                             
                                                                                                                                
1:58:58 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE  JOSEPHSON inquired  where the  equipment is  made                                                               
for the aforementioned sea lifts.                                                                                               
                                                                                                                                
MR. BUTT answered that different  pieces of equipment are sourced                                                               
in different places.  A lot of it  would be in Alaska and some of                                                               
it  would be  out-sourced to  places that  have heavy  equipment.                                                               
The main reactors  and re-boilers for the acid  gas removal units                                                               
(AGRUs) are 130 feet tall, 28  feet wide, 6-8 inches thick on the                                                               
plate, and there are  only a few places in the  world that can do                                                               
that.   Korea is one place  and other places are  being looked at                                                               
in efforts to  be as competitive as possible.   There is no place                                                               
in the  U.S. right now  that can  fabricate a vessel  that large.                                                               
The  barges that  would be  used will  probably by  sourced in  a                                                               
range of  places including  the U.S.   The  camp can  probably be                                                               
sourced in Alaska, which is good  because then it doesn't have to                                                               
be moved as far.  Everything  is being done to ensure marrying up                                                               
global LNG  expertise with local construction  knowledge to drive                                                               
down the cost of  supply.  Some of the big  turbines will be made                                                               
in the  Lower 48, but  there are only a  couple of places  in the                                                               
world that make  those.  Some of the big  reactor vessels will be                                                               
made in  Asia; again, only a  couple of places in  the world make                                                               
those.  The most efficient source  for each will be used in order                                                               
to drive down cost of supply.                                                                                                   
                                                                                                                                
REPRESENTATIVE JOSEPHSON asked what gravel source will be used.                                                                 
                                                                                                                                
MR. BUTT  pointed out on  slide 9 that  there is a  gravel source                                                               
about two and  a half miles down  the road from the  west dock at                                                               
Prudhoe Bay  (depicted in  yellow) to  the central  gas facility.                                                               
He noted that the  picture of gravel on slide 9  shows that it is                                                               
a good  gravel find.  Finding  the gravel source was  progress on                                                               
de-risking because  a year ago  it was unknown whether  there was                                                               
gravel, which was  a risk.  Now the optimization  study is needed                                                               
for getting the costs down.                                                                                                     
                                                                                                                                
2:02:04 PM                                                                                                                    
                                                                                                                                
MR. BUTT  turned to slide  10, "Labor Update," advising  that the                                                               
labor study  is progressing  with the  help of  large third-party                                                               
companies to  understand how to  source the labor.   The estimate                                                               
is still  for 9,000-12,000  jobs and  it will  be hard  to source                                                               
that  labor.   He  drew  attention  to  the graph  depicting  the                                                               
projects in the  Western U.S. that are  currently consuming labor                                                               
for the  next several years.   He explained that while  the graph                                                               
shows a tapering off in the  amount of labor that will be needed,                                                               
that is  not really the case.   Rather, the graph  tapers because                                                               
the  forecaster's ability  to capture  information on  those jobs                                                               
goes away.   To show the enormity and the  context of 9,000 jobs,                                                               
he pointed  out that this number  is equivalent to all  the labor                                                               
working on similar  activities in all of the  Western U.S. coming                                                               
to work on  one project in one  place.  So, the  challenge is how                                                               
to source this labor efficiently  to maximize use of Alaskans and                                                               
source the labor that will be needed.                                                                                           
                                                                                                                                
2:04:12 PM                                                                                                                    
                                                                                                                                
MR. BUTT  noted that slide  11, "Logistics Update," is  about how                                                               
to use  sea, road,  rail, and  air to move  facilities.   He said                                                               
each of the  yellow boxes [shown on  the map of the  state] has a                                                               
logistics  plan for  the  facilities that  would  be required  in                                                               
those places.  For example,  hundreds of thousands of trucks will                                                               
be required  to move all the  facilities and all the  pipe across                                                               
the state.   The  needs of  each individual  part of  the project                                                               
must be considered in relation to  the needs of each of the other                                                               
parts of the project.  The needs  for the same skill sets must be                                                               
considered  and phased  and integrated  so as  not to  compromise                                                               
each of the  other parts.  Different ways to  execute the project                                                               
are being looked at in order  to be as efficient as possible; for                                                               
example,  whether something  could  be done  by  rail instead  of                                                               
truck  or how  to use  as little  air transportation  as possible                                                               
because it is the most expensive method.                                                                                        
                                                                                                                                
2:05:55 PM                                                                                                                    
                                                                                                                                
MR.  BUTT drew  attention  to slide  12, "Contracting  Approach,"                                                               
explaining that  a contracting model  is being put  together that                                                               
is  grounded in  the  philosophy  of how  to  combine global  LNG                                                               
knowledge with  local Alaska experience.   The two  parties don't                                                               
have a  lot of experience  with each  other, so people  are being                                                               
introduced to each  other to build a relationship  and create the                                                               
ability  to  have  capacity  to  execute  this  project.    Local                                                               
Alaskans know  regulations and communities.   Global constructors                                                               
have  large  capabilities  and experience  building  these  large                                                               
vessels.   The  near-term  contracting goals  are  to finish  the                                                               
market engagement with all the  primary bidders, conduct business                                                               
information  sessions, get  FEED  bid information  from the  main                                                               
contractors, have  networking forums  where these groups  talk to                                                               
each  other,  and  complete focus  group  sessions  on  execution                                                               
plans.   Mr. Butt  noted that  over 100  contractors have  so far                                                               
worked on the project.                                                                                                          
                                                                                                                                
2:08:25 PM                                                                                                                    
                                                                                                                                
MR.  BUTT addressed  slide  13,  "Summer Field  Season/Regulatory                                                               
Work," pointing out  that everything being done is  to inform the                                                               
resource   reports   and  file   for   an   application  for   an                                                               
environmental impact statement.   Exhibits A-D are  all about the                                                               
corporate framework  or structure  of the  entity that  makes the                                                               
application.   Exhibit  E  is about  the  safety and  engineering                                                               
information that underpins  it.  Exhibit F is what  is called the                                                               
resource reports,  which are  the 13 reports  listed in  the left                                                               
purple  box.   Draft  1 was  submitted last  year  and was  about                                                               
10,000  pages.   Draft 2  is  being prepared  now for  submission                                                               
sometime between February and May.   Each of the resource reports                                                               
focuses  on one  of the  thirteen things;  for example,  Resource                                                               
Report 7 will  be about 2,000 pages  reporting everything learned                                                               
about the different soils in  all the different places across the                                                               
state  and why  it is  thought that  a GTP  can be  built in  the                                                               
north, a pipeline through the center  of the state, and an LNG on                                                               
the eastern  side of Cook  Inlet.  This must  be done for  all 13                                                               
resource  reports and  those resource  reports  then trigger  the                                                               
environmental impact  statement (EIS) application, which  is what                                                               
FERC uses  as the umbrella  organization to get all  the agencies                                                               
to work with the project team to progress the EIS.                                                                              
                                                                                                                                
MR. BUTT  said the project  continues to have great  support from                                                               
the  Alaska Delegation  and  the  doors are  always  open to  the                                                               
project when  going to talk to  the federal regulators.   It is a                                                               
huge amount  of work and  it won't  really be known  what federal                                                               
regulators are thinking  until the application is  filed and they                                                               
come back under the EIS and  tell the team how the project looks.                                                               
Until that happens it is still  a regulatory risk - anything done                                                               
without that  permit in hand  may be  frustrated.  A  quality job                                                               
must  be done  on  filing the  resource reports  as  part of  the                                                               
application  so the  permit risk  can be  de-risked.   That is  a                                                               
multi-year process and underpins  everything the project is doing                                                               
in Pre-FEED.                                                                                                                    
                                                                                                                                
2:11:25 PM                                                                                                                    
                                                                                                                                
MR. BUTT moved to slide 14,  "Forward Plans," to discuss how Pre-                                                               
FEED fits into  the bigger puzzle.  First, a  concept is selected                                                               
and a determination  made on what the project will  look like and                                                               
how to  build it.   Concept work was  done in 2012  through early                                                               
2014 to decide  where the different pieces would go  and how they                                                               
would  be sized.   Then,  in Pre-FEED  it is  made sure  that the                                                               
concept   is  right   via  integrated   hydraulic  modeling   and                                                               
composition modeling.   Pre-FEED is moving  everything needed for                                                               
the permit and  it is all the cost and  schedule estimates.  This                                                               
information is  then used to decide  whether to go into  the FEED                                                               
phase.   In FEED  the spending  is ramped  up and  the regulatory                                                               
machine continues  to be fed.   Once the EIS is  filed the amount                                                               
of work goes up, not down.                                                                                                      
                                                                                                                                
2:12:19 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE HERRON posed a scenario  in which a break is taken                                                               
between Pre-FEED and FEED, and asked  how long the pause could be                                                               
between the two phases before a "stale date" is reached.                                                                        
                                                                                                                                
MR. BUTT  replied that  discussions have been  held with  FERC on                                                               
this topic and  the answer is yes,  a lot of the  work would have                                                               
to be redone.   Geotechnical and geophysical soil  borings do not                                                               
expire; however,  cultural heritage, socio-economic,  design, and                                                               
emissions  data do  expire.   Also,  while not  always the  case,                                                               
regulations  tend  to get  more  difficult  with  time.   So,  in                                                               
addition  to having  an expiration  date on  large pieces  of the                                                               
project's  work, the  hurdles that  must be  cleared to  permit a                                                               
project of this magnitude tend to get larger, not smaller.                                                                      
                                                                                                                                
REPRESENTATIVE  HERRON inquired  as to  how long  that period  of                                                               
time might be.                                                                                                                  
                                                                                                                                
MR. BUTT responded  that after a year things start  to get really                                                               
difficult because  FERC must  be given a  reason to  keep working                                                               
with the project owner.  If FERC  was to be told that the project                                                               
will be  pausing for  a while,  a path forward  would have  to be                                                               
painted because  the agency has built  a team and worked  to help                                                               
the Alaska  LNG Project instead  of the dozens of  other projects                                                               
that are vying  for the agency's time.  So,  FERC doesn't receive                                                               
that information well given it is  trying to do everything it can                                                               
to  meet its  mandate as  the  umbrella organization  to get  the                                                               
right  energy mix  for  the  country and  this  project has  been                                                               
represented as a part of that  puzzle.  The project has had great                                                               
support   all   the   way  up   through   the   current   federal                                                               
administration.                                                                                                                 
                                                                                                                                
2:16:06 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE   JOSEPHSON  related   that   some  Alaskans   are                                                               
concerned  and cynical  because they  believe this  effort is  to                                                               
save face, is impractical, and won't  happen.  Also heard is that                                                               
this  is an  effort to  just preserve  the lease  so there  is no                                                               
litigation.  Qualifying  that he himself doesn't see  it this way                                                               
because he  can see Mr.  Butt's and the contractors'  passion for                                                               
the project, he asked what Mr. Butt would say to these Alaskans.                                                                
                                                                                                                                
MR. BUTT  answered he  has heard the  cynicism when  talking with                                                               
people at  community meetings and  it is fair  because monetizing                                                               
North Slope resources has been looked  at many times.  Every time                                                               
folks  try  to  monetize  the   gas  resources  they  might  spin                                                               
something up  but then they stand  it down.  He  said the analogy                                                               
he likes to use is from  the old Peanuts cartoon in which Charlie                                                               
Brown tries  to kick the football  and every time Lucy  moves it.                                                               
Different folks have different ideas  on whether they are Charlie                                                               
Brown or  somebody else is  Lucy.   The cynicism is  fair because                                                               
the project  has started and  stopped and people have  never seen                                                               
all  four parties  try  to  do the  project  together  or do  the                                                               
project  together  successfully.    So  until  that  happens  the                                                               
cynicism is well  rooted.  Mr. Butt pointed out  this project has                                                               
made  a lot  more progress  than  any others  and cautioned  that                                                               
philosophies can  become self-fulfilling.  If  people don't think                                                               
it is  going to  work and  don't try  to help  it work,  they are                                                               
probably going to be right.   However, if people do think it will                                                               
work  and  are willing  to  help  make  it  work, then  they  are                                                               
probably right.   That is why  he is talking to  legislators, the                                                               
board  of directors  representing the  owners who  are skeptical.                                                               
If it is  thought that today's market environment  is never going                                                               
to change, then the project probably  shouldn't be done.  But, if                                                               
it is  thought that today's  market environment will  change, and                                                               
the  four  parties  can establish  enough  alignment  to  deliver                                                               
product  at the  lowest possible  cost,  then this  work is  well                                                               
founded.  The FERC  work must be kept going in  order to keep the                                                               
option going  for continuing the  project.  When the  parties are                                                               
aligned they have trust in each  other and that is the confidence                                                               
that is needed to go into FEED.                                                                                                 
                                                                                                                                
2:20:56 PM                                                                                                                    
                                                                                                                                
MR. BUTT  returned to  slide 14,  reiterating that  confidence is                                                               
what it  takes to move from  Pre-FEED to the next  phase.  Moving                                                               
along there is a  chance to stop the project if  that is what all                                                               
the parties choose  to do, but under the  joint venture agreement                                                               
the  parties have  agreed  to  finish the  work  scopes in  2016.                                                               
Those  work  scopes  include  completion  of  [Pre-FEED].    What                                                               
happens in 2017 is wide open  because there is no budget in 2017.                                                               
Really big decisions  will have to be made in  2017 about ramping                                                               
up the  risk, that there  is the  confidence that FERC  will keep                                                               
going and  the necessary  permits will be  received and  that the                                                               
four parties  can work  with each  other.  When  one of  the four                                                               
parties has  a problem, he specified,  then he has a  problem and                                                               
he must find a way to  bridge across that because every party has                                                               
to be  moving through the  gate together or nobody  moves through                                                               
the gate.   And it  must be done  in a  way that there  is enough                                                               
confidence for the parties to want  to go execute this project at                                                               
$45-$65 billion and  spent in a way that gets  LNG cost of supply                                                               
low enough that the project can  deliver gas to buyers for a long                                                               
enough time below  what the buyers could get it  for from anybody                                                               
else and  there is still  money left  over to make  Alaskans, who                                                               
are  the investors,  happy.   He  said the  cost  of the  concept                                                               
selection  stage was  $30  million a  year for  a  total of  $107                                                               
million over two  and a half years.  During  the current Pre-FEED                                                               
stage the cost has been $30 million  a month, for a total of $376                                                               
million spent  over the last  18 months.   In FEED the  amount of                                                               
work goes through  the roof, with expenditures  being $30 million                                                               
a week.  In execution expenditures will be $30 million a day.                                                                   
                                                                                                                                
MR. BUTT  urged that the four  [stages] depicted on slide  14 not                                                               
be looked  at as just abstractions.   Rather, it is  a process to                                                               
ask whether the  cost has been driven down enough  to be ready to                                                               
invest that kind of  resource - to go from $30  million a year to                                                               
$30 million a month  to $30 million a week to  $30 million a day.                                                               
So, how  to do that?   The pipeline size  will be figured  out in                                                               
April and  work will  be done  with AGDC  to identify  and define                                                               
exactly where  the interconnection points, the  offtakes, will be                                                               
located.     The  authorizing  legislation  states   up  to  five                                                               
interconnection  points, but  the project  team is  open to  some                                                               
flexibility and  would like to see  the number around five.   The                                                               
integrated model will be completed so  that all the pieces can be                                                               
known.  Once  all the pieces are known, all  the other things can                                                               
be   done,  such   as  checking   the  maintainability   and  the                                                               
availability,  making sure  that  everything  works, getting  the                                                               
deliverables done, and driving down cost.                                                                                       
                                                                                                                                
2:24:23 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE  TARR  inquired as  to  how  much more  confidence                                                               
there will  be in the  budget numbers,  and reducing the  size of                                                               
the  range between  $45 and  $65  billion, once  the pivot  point                                                               
between Pre-FEED and FEED is reached.                                                                                           
                                                                                                                                
MR.  BUTT  replied that  coming  out  of  Pre-FEED the  cost  and                                                               
schedule  will absolutely  be defined  to a  much tighter  range.                                                               
The pieces  will be broken down  to show what is  needed and what                                                               
is contingency.   The  costs will be  broken into  three buckets:                                                               
1) premise  - what it takes  to build this; 2)  contingency - the                                                               
extra that will be held for  uncertainty since it will be several                                                               
years before the  start of construction during  which time things                                                               
can change; and 3) owner's cost  - those monies needed to execute                                                               
that project.   Effort will be  made to drive all  three of those                                                               
down, but the  focus will be on premise and  premise is driven by                                                               
the equipment, steel, machinery, and so forth that is bought.                                                                   
                                                                                                                                
REPRESENTATIVE  TARR recalled  that  in his  State  of the  State                                                               
address,  Governor  Walker  said  he  hoped  to  have  commercial                                                               
contracts  for legislators  to consider  during this  legislative                                                               
session.  She  offered her understanding that  Governor Walker is                                                               
interested in  the project  financing model  and asked  how those                                                               
two are going to intersect at that stage.                                                                                       
                                                                                                                                
MR. BUTT  suggested this question  be directed to the  four party                                                               
representatives who will be before  the committee on 1/27/16.  He                                                               
explained that  from a project  perspective, his role is  to make                                                               
sure the work gets  done in the right way and  all the pieces are                                                               
kept together.  He allowed  there are some significant commercial                                                               
challenges  and the  questions are  whether the  parties want  to                                                               
work past them and can they work past them.                                                                                     
                                                                                                                                
2:27:17 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE  SEATON offered  his appreciation  for Mr.  Butt's                                                               
work and for Mr. Butt directing  his talk to committee members as                                                               
the board of directors of an owner  of the project.  As an owner,                                                               
he  noted, the  State  has  a 12.5  percent  royalty  and a  12.5                                                               
percent  production tax,  both  of  which are  taken  as gas  and                                                               
thereby  make the  State  a  25 percent  owner.   Expressing  his                                                               
concern  about the  State's current  fiscal  condition, he  noted                                                               
that the  State is paying  35 percent  of the upstream  costs via                                                               
development credits  while the State's midstream  ownership is 25                                                               
percent.  He asked how Mr.  Butt sees the influence of that issue                                                               
on the Alaska LNG Project.                                                                                                      
                                                                                                                                
MR.  BUTT deferred  to  each of  the four  parties  that will  be                                                               
before the  committee on 1/27/16.   Offering a  unifying thought,                                                               
however,  he  said  investors,  whether  direct  participants  or                                                               
lenders,  want to  understand how  their capital  is at  risk and                                                               
what it will take to get  that capital returned in a safe manner.                                                               
Whether it  is investment tax credits  or any other element  of a                                                               
tax structure, which in Alaska  is a royalty structure, they want                                                               
to  understand  how  that  influences   the  different  flows  of                                                               
capital.   He  added that  he  thinks that  the tax  credit is  a                                                               
little bit different than an investment.                                                                                        
                                                                                                                                
2:30:26 PM                                                                                                                    
                                                                                                                                
REPRESENTATIVE JOSEPHSON  related that  some of  his constituents                                                               
have  said legislators  were  wrong in  voting  last November  to                                                               
invest another  $150 million and that  instead consultants should                                                               
be paid to go  back three years and look at  ideas such as having                                                               
tankers  off  the  North  Slope  and  depositing  excess  in  the                                                               
Aleutian Islands until such time as  the market is ready and then                                                               
have tankers  go west  from there.   He  asked whether  there has                                                               
been discussion of options that do not require a pipeline.                                                                      
                                                                                                                                
MR. BUTT responded that the task  in the concept stage is to look                                                               
at  everything  that  can  be   thought  of;  for  example,  even                                                               
submarines under  ice was looked  at.  The main  challenge moving                                                               
LNG in  the Arctic  is that it  is the wrong  time.   Buyers want                                                               
absolute certainty  in January and February  because those buyers                                                               
have put their whole economy at  risk in the hands of the company                                                               
from which  they are  buying their  energy.   If the  LNG project                                                               
doesn't make a  delivery, that economy goes down  when the lights                                                               
and power are lost.   It is a big deal to  deliver reliably.  The                                                               
parties in this  venture have the ability  to demonstrate success                                                               
in  a wide  range of  solutions and  build confidence  in buyers.                                                               
The  costs for  long-term seasonal  storage  of LNG  are off  the                                                               
chart,  he  advised,  because  the  LNG  is  so  cold  that  very                                                               
specialized materials must  be used to store it.   The metals and                                                               
insulation  are  ridiculously  expensive.   The  foundations  are                                                               
dozens  of  feet  thick  depending   on  location  because  every                                                               
molecule in  that tank must be  kept at -260 degrees  F.  Storing                                                               
LNG  for  anything  more  than  a period  of  days  is  extremely                                                               
difficult and  requires continuous  energy because  in comparison                                                               
to  LNG the  world is  on fire  and LNG  is constantly  trying to                                                               
return to  a gaseous state.   In  the LNG business  everything is                                                               
done to get LNG storage to nothing  - in a perfect world it would                                                               
be liquefied and immediately put on a transport ship.                                                                           
                                                                                                                                
MR.  BUTT  shared  that  another  way   to  do  this  is  to  use                                                               
icebreaking tankers.   A project called Yamal decided  to do this                                                               
across  the  Arctic, but  is  having  tremendous difficulty;  the                                                               
reliability in  winter is  really challenged  and the  project is                                                               
having a very hard time getting  finances.  He added that in 2012                                                               
and 2013 he  was often asked why  not have the project  do gas to                                                               
liquids  (GTL).   The reason,  he explained,  is that  LNG is  95                                                               
percent efficient - 95 percent of  the amount of energy that goes                                                               
into  the system  is delivered  to  the customer.   However,  the                                                               
efficiency for  GTL is  60-65 percent because  so much  energy is                                                               
used  to convert  the gas  to  a wax  to  break it  to a  liquid.                                                               
Additionally,  in the  Arctic, GTL  takes  tremendous amounts  of                                                               
water and  there is not  that water.   Plus, with GTL  a pipeline                                                               
would  not be  built  and so  the benefit  of  delivering gas  to                                                               
Alaskans would go away.                                                                                                         
                                                                                                                                
CO-CHAIR  NAGEAK  remarked that  things  have  changed since  the                                                               
1970s when it was a whole lot  colder.  There is now flooding and                                                               
earthquakes in Barrow and things are  much more costly due to the                                                               
changes.  He thanked Mr. Butt for the presentation.                                                                             
                                                                                                                                
2:38:14 PM                                                                                                                    
                                                                                                                                
ADJOURNMENT                                                                                                                   
                                                                                                                                
There being no  further business before the  committee, the House                                                               
Resources Standing Committee meeting was adjourned at 2:39 p.m.                                                                 

Document Name Date/Time Subjects
1.25.16 HRES - AK LNG PJ - Steve Butt.pdf HRES 1/25/2016 1:00:00 PM